Schedule Risk Analyses

 

A schedule risk analyses incorporates real world risks to your project schedule to create a more realistic schedule. A schedule risk analyses also gives you an insight in the risks with the biggest impact on your schedule. This greatly improves your project management and increases the chance that you deliver on-time and within budget.

To create a schedule risk analyses you can follow these steps:

  1. Set up a deterministic project schedule without the slack for the occurrences of the project risks
  2. Set up a project risk register with risk description, likelihood, impact on schedule in days, schedule phase or activity in which the risk can occur
  3. Connect deterministic schedule and risk register on phase and activity
  4. Perform a Monte Carlo analyses of the connected planning

 

Project Risk Online specialises in project risk management. We support projects around the world with schedule risk analyses for projects in IT, infrastructure, energy and construction. If you already have a proper deterministic schedule and a risk register we can do the Monte Carlo analyses for your projects. If required we can also support you with setting up and maintaining your project planning and risk register.